$5.5 Million Renovation

WLHC Renovation Overview

The WLHC renovation began during the Fall 2015, with the complete renovation scheduled to be done by Fall of 2017. The renovation encompasses many projects and has been split into “phases”.

Completed Phases

Phase 1 - HVAC system providing all spaces in the facility with centralized heating and air conditioning.

Phase II is a new north community entrance for the building, a new expanded fitness/exercise space, the pool area, renovation of the WLHC locker rooms and new family changing rooms.

Phases in process

Phase III and IV have begun, with the hopes of completion by the end of the summer of 2017. Projects in these phases include the 2ndfloor public restrooms, commons areas, fitness classroom and racquetball courts. Also included in this phase is signage throughout the building.